Grinding - Downtime
Grinding – Downtime Entry Guide

1. Login and Navigate to Grinding – Pebble Crusher
- Login into Optimum and navigate to the Data Portal.
- Under Data Portal, click Shift Logs and expand the Grinding section.
- Click Grinding – Pebble Crusher to open the data entry form.
Under Select Data Period, choose the shift you want to enter.
Shift Status Types:
- Not Entered – No data saved
- Unconfirmed – Data saved but not confirmed
- Confirmed – Finalised and locked
3. Entering Pebble Crusher Data
Entering Downtime Data
Enter downtime Data in each row as required for the fields below:
- Stop : Enter time in the format(hh:mm) it is the time when the equipment stopped
- Start : Enter time in the format(hh:mm) it is the time when the equipment started again
- Ton/h
- Status
- Planned
- Equipment
- Section
- Keyword
- Description
- What/Action
- Type
- Asset Per
Note: Start Time in each row should be after the Stop Time
4. Save Entry- Click Save at the bottom of the form to store the shift entry.
- Once saved, the shift becomes Unconfirmed.
- After saving, you may confirm the entry if you have the required access.
- Confirming locks the shift — no further changes can be made unless it is unconfirmed first.
- Click Unconfirm if you need to edit a confirmed entry (access‑dependent).
- Deletes the shift entry (only available to authorised users).