Change Production Numbers
How to Change Production Numbers with an audit trail.
-
Locate the shift or day you want to update.
On the Production grid, find the specific Shift or Day entry that requires a change.

-
Open the Audit window.
Double-click the row to open the Audit pop-up window.
Note: Only users with L3 access or higher can update Actual Production values. -
Enter the new Actual Production value.
-
Type the updated Actual value into the field provided.
-
Enter the reason for the change in the comments box.
-

-
Save the update.
Click Save at the bottom of the pop-up window to apply the change. -
Confirm the adjustment.
The updated Actual Production value will now appear in bold in the grid, indicating it has been modified from the original entry.