CCD-Fresh Water Totalizer

1. Login and Navigate to CCD – Fresh Water Totalizer
- Login into Optimum and navigate to the Data Portal.
- Under Data Portal, click Shift Logs and expand the CCD section.
- Click CCD – Fresh Water Totalizer to open the data entry form.
2. Selecting the Shift to Enter
Under Select Data Period, choose the shift you want to enter.
Shift Status Types:
- Not Entered – No data saved
- Unconfirmed – Data saved but not confirmed
- Confirmed – Finalised and locked
3. Entering Slaker Data
Enter the Totallizer values at start of shift and end of shift for the following
- Well Pump
- WW-01
- WW-08
- WW-02
- WW-03
- WW-09
- WW-02
- WW-05
- WW-04
- To Tongo
- Point Totalizer
- Water Truck Sejorong
- Supply To Townsite
- Suply to Concentrator
- Concentrator WTP
- 32-PU-08
- 31-PU-015
- Supply to 130/106
- WW-04 to SWIS
- Supply to Trakindo
- To Solar Cell Power Plant
- Fire Pump A
- Fire Pump B
4. Save Entry
- Click Save at the bottom of the form to store the shift entry.
- Once saved, the shift becomes Unconfirmed.
5. Confirm Entry
- After saving, you may confirm the entry if you have the required access.
- Confirming locks the shift — no further changes can be made unless it is unconfirmed first.
6. Unconfirm Entry
- Click Unconfirm if you need to edit a confirmed entry (access‑dependent).
7. Delete Entry
- Deletes the shift entry (only available to authorised users).